IBK REF Information October 15th 2026

See current projects here: REF Projects

QTR 4/2026

QTR 1/2027

HPQ construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines Hexapod, 10MN universal testing machine).

NCCR Demonstrator

The NCCR demonstrator can be inaugurated in November.

Defect cherry picker

The Manitou cherry picker in Bauhalle is defect and we have to replace it. Therefore a Haulotte rental machine is available until we have a new solution.

Measurement equipment

Because we have many active projects (53) this semester the measurement equipment is running out.
Therefore do an early planning for sensors and measurement setups and try to have as many sensors as it makes sense.

Lack of space in Bauhalle

Also space in Bauhalle is limited because of many projects. Please check to dispose as much material early if it is no longer required and also free project space if no longer required.

In case of accidents

https://ethz.ch/staffnet/en/service/safety-security-health-environment/accident.html

  • Hexapod (Chatzi): An evaluation report for possible new locations was received.
    Location on old strong floor is preferred. Feasibility study is in progress.
    This includes a test with the air cussions on the old strong floor in November.
  • 15MN machine (Taras)
    Tendering finished. Two bids were submitted. Decision by end of October 2026.

IBK REF Information September 3rd 2026

See current projects here: REF Projects

QTR 3/2026

QTR 4/2026

HPQ construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).
Visitors tell: https://www.alumni.ethz.ch/en/news/alumni-news/2026/05/hpq-das-physikgebaeude-der-zukunft.html

Hexapod (Chatzi)

For placing the Hexapod on the old strong floor a test with the existing air cussions is planned. This will influence the other projects on the old strong floor.
Today these tests are planned for November. Before construction works, especially in floor B will be performed.

NCCR Demonstrator

In HIF couryard (north side) the construction works for the NCCR demonstrator should be finished by end of October.

10MN Testing machine (Taras)

The tender process is ongoing and we expect to have a decision for a company till end of September.
Afterwards an engineering phase will be started to also plan the reconstruction for the foundation.

Procurement

If you have material to order please:

  • Always tell the deliverer to mention your name on the address
  • Inform Bauhallenteam about your order if it will be delivered to the IBK laboratories directly
  • Contact Bauhalle to “perhaps” save money before ordering – we have good conditions for many shops.
    You can also check the ETHIS shops.

Fire safety training
Recommended, interesting action course, not at all just for FireSIM workers:
https://ethz.ch/staffnet/en/service/safety-security-health-environment/course-calendar/fire-safety-trainings.html

And here is how to cope with “summer” or experimental heat
https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2026/07/was-tun-bei-sommerhitze-am-arbeitsplatz.html

  • Hexapod (Chatzi): An evaluation report for possible new locations was received.
    Location on old strong floor is preferred. Feasibility study is in progress.
  • 15MN machine (Taras)
    Tendering documents almost finished. The official call for proposals will start in August.

IBK REF Information June 18th 2026

See current projects here: REF Projects

QTR 2/2026

QTR 3/2026

Revision and upgrade Schenck

Both Schenck machines are serviced and got a new controller. Pay attention that also the software changed. Contact Bauhallenteam if you plan tests using the Schencks.

HPQ construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).
Visitors tell: https://www.alumni.ethz.ch/en/news/alumni-news/2026/05/hpq-das-physikgebaeude-der-zukunft.html

NCCR Demonstrator

In HIF couryard (north side) the construction works started for the NCCR demonstrator.
There can be vibrations and difficulties for deliveries until end of August 2026.

Schedule Autumn Semester

make sure to propose ALL student projects until July 19th 2026 here:
Propose Project
We also wish to get applications for other projects a early as possible. You can also use the upper link.

Bauhalle bookings

Beside our booking system for equipment (Outlook calendars) all sensitive experiments and those who have potential to influence others MUST be scheduled by using the
“Bauhalle Bauhalle HIF C51” hifb51@ethz.ch
calendar. This can be done by inviting the calendar to your meeting.
This is required because some projects had to be shifted in past because of influencing others.

NEW safety regulations at ETH

exist since June 1st. Read about it here: https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2026/05/working-safely-at-eth-new-regulations-come-into-force.html.

Experimental guest groups

Beside group de Wolf (BAUG) and Boltshauser (ARCH), the Chair of Structural Design by Prof. Dr. Jacqueline Pauli will also join Bauhalle in the future.

    SGU crane introduction
    Beside the Bauhallen course there is also an SGU crane course:
    https://ethz.ch/staffnet/de/service/sicherheit-gesundheit-umwelt/kursangebot/uebersicht-kursangebot.html#:~:text=Kran

    Fire safety:
    There is also an internal fire safety course: https://ethz.ch/staffnet/en/service/safety-security-health-environment/course-calendar/fire-safety-trainings.html
    Bauhallenteam can highly recommend that action course.

    • Hexapod (Chatzi): An evaluation report for possible new locations was received.
      Location on old strong floor is preferred. Feasibility study is in progress.
      Also a test with the existing air cussions is planned. This will influence the other projects on the old strong floor – we will inform if there are more details.
    • 15MN machine (Taras)
      Tendering documents almost finished. The official call for proposals will start in August.

    IBK REF Information – May 6th 2026

    See current projects here: REF Projects

    QTR 2/2026

    QTR 3/2026

    Revision and upgrade Schenck

    In the first week of June both Schenck universal testing machines will get a new controller. The machines can not be used for approximately 2 weeks. Please check the booking calendars or ask Bauhallenteam.

    HPQ – construction site

    More information: HPQ construction
    Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).

    NCCR Demonstrator

    In HIF couryard (north side) the construction works started for the NCCR demonstrator.
    There can be vibrations and difficulties for deliveries in the next 4 weeks.

    High season

    We’re getting closer to the end of the semester, and projects are getting busier. Make sure to ask Bauhallenteam for support till Friday for the following week.
    We also realize that not all students receive the same level of support from their project managers which costs much more effort to Bauhallenteam.
    Please make sure to ensure – also for the next semesters:

    • Student projects are managed by an IBK ELU.
      The project manager is the main responsible and main supporter in the lab.
    • Students are introduced when starting in laboratories
      Find all information in our Sharepoint site.
    • Bauhalle is informed about the student projects
    • Setup is ready for assembly when student is starting!
    • Plan a kickoff meeting early
      • Min. 1 month before student starts

    1st aid course @ ETH
    Refresh your safety skills:
    https://ethz.ch/staffnet/en/service/safety-security-health-environment/course-calendar/details.14209o.html

    Check what others do:
    Power tools safety: https://www.youtube.com/watch?v=NGeJ-oyDlSI

    • Hexapod (Chatzi): An evaluation report for possible new locations was received.
      Location on old strong floor is preferred. Feasibility study is in progress.
    • 15MN machine (Taras)
      Technical specification document is ready for tender.

    IBK REF Information – April 1st 2026

    Running Projects

    See current projects here: REF Projects

    QTR 2/2026

    QTR 3/2026

    Revision and upgrade Schenck

    In June both Schenck universal testing machines will get a new controller. The machines can not be used for approximately 2 weeks. Please check the booking calendars.

    HPQ – construction site

    More information: HPQ construction
    Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).

    Testing the switchover involves a residual risk of a brief power outage April 21st

    The redundant connection and its switchover logic will be tested on 21 April 2026. A backup date of 5 May 2026 has been set aside for any necessary repeats. Safety measures will prevent interruption of the power supply. Nevertheless, there is a slight residual risk of a brief (<1 minute) power outage between 9 a.m. and 4.30 p.m., for example due to faulty connections.

    Large specimen

    We got 6 large wooden specimen to Bauhalle. They are part of the Dock A project for airport Zürich.
    After testing the specimen we try to realize another loading platform in Bauhalle out of it.

    SSHE courses
    Keep you up to date in safety with the ETH courses:
    https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2026/03/schulungsangebot-sgu-schulungskalender.html

    Check what others do:
    At Dispendix, a Frauenhofer Spin-off

    • Hexapod (Chatzi): An evaluation report for possible new locations was received.
      Location on old strong floor is preferred. Feasibility study is in progress.
    • 15MN machine (Taras)
      Technical specification document is ready for tender.
    • NCCR demonstrator in the HIF couryard:
      Construction will start in April.

    IBK REF Information – March 3rd 2026

    See current projects here: REF Projects

    QTR 1/2026

    QTR 2/2026

    Working hours Bauhalle

    Opening hours in Bauhalle and in the FireSimulator lab are 7:00-17:00. In this period support from Bauhallenteam can be guaranteed. Please make sure to inform Bauhallenteam in writing if you have to work outside these hours. More about safety regulations here: https://ethz.sharepoint.com/sites/PRO-BAUG-00003828/SitePages/CollabHome.aspx

    Space in Bauhalle

    There is a lot of material to be stored in Bauhalle for the next months. Please check to dispose as much material early if it is no longer required.

    Revision and upgrade Schenck

    Hydraulics and Mechanics of both Schenck machine were serviceed in the last week of February.
    There is a second phase in June where the new controller will be installed.

    HPQ – construction site

    More information: HPQ construction
    Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).


    Introduction courses
    Please register for the new courses & share with those interested:
    Crane introduction: Are planned in week 10 and 11.Please contact Bauhallenteam if you want to be on the waiting list, also for the common introduction.

    Youth Work
    Dangerous work is generally prohibited for young people (up to their 18th birthday). ETH Zurich takes into account that young people still have little experience, their awareness of dangers is not yet fully developed and they are less capable than adults.
    see also: https://ethz.ch/staffnet/en/service/safety-security-health-environment/health-protection.html

    First Aid Team
    ETH Zurich’s First Aid Team is looking for new members for various areas at Zentrum, Hönggerberg and external locations.
    https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2026/02/neue-mitglieder-EHT-gesucht.html

    • Hexapod (Chatzi): An evaluation report for possible new locations was received.
      Location on old strong floor is preferred. Feasibility study is in progress.
    • 15MN machine (Taras)
      Technical specification document is in preparation by Bauhallenteam.
    • NCCR demonstrator in the HIF couryard: Construction will probably start in April 2026.
    • Schenck Service & upgrade
      see info above.
    • Welding-shop in HIF B floor
      Henry set up a welding toolshop in HIF B-floor in collaboration with the D-BAUG toolshop (ongoing).

    IBK REF Information – February 11th 2026

    See current projects here: REF Projects

    QTR 1/2026

    QTR 1/2026

    Project proposal – DEADLINE

    Deadline for new student projects in springsemester 26 is Friday 16th of January 26.
    Use the following link for applying: ProjectProposal

    Revision and upgrade Schenck

    Both Schenck machine will be services end of February (23 – 29. February) and can not be used in this time. Also experiments in Bauhballe using the hydraulic aggregates can be influenced.
    In a second period in June the controller will be renewed.

    HIC Building and Makerspace

    A Makerspace is planned in HIG garage for D-ARCH and D-BAUG which could also be interesting for Bauhalle. In combination with the new planned HIC student project house building there could be new opportunities for experimental research. A needs analysis is currently underway.
    Links:
    https://ethz.ch/en/campus/development/construction-projects/hic-projekt.html
    https://sph.ethz.ch/news/challenge-build-hci-building
    https://ethz.ch/de/news-und-veranstaltungen/eth-news/news/2020/10/wo-studierende-kuenftig-ihre-ideen-entfalten.html


    Introduction courses

    Please register for the new courses & share with those interested:

    https://doodle.com/sign-up-sheet/participate/dcd5c871-24f3-433d-8017-aabb88616625/select

    Please contact Bauhallenteam if you want to be on the waiting list.
    Crane introduction: There will be a crane introduction afterwards, contact us if you want to be on the waiting list.

    Research data management (data safety)
    Did you know, under the Guidelines for Research Data Management (RDM) effective since July 2022, ETH Zurich mandates a standard retention period for experimental data.

    Standard Retention Period: Minimum of 10 Years: As a general rule, research data (including measurement data) necessary for validating published research results must be retained for at least 10 years after the project’s completion or publication.

    • Hexapod (Chatzi): An evaluation report for possible new locations was received.
      (1) location in nothern part of Bauhalle with restrictions to horizontal dynamic capacity
      (2) location on old strong floor
    • 15MN machine (Taras)
      Specification document is in preparation by Bauhallenteam.
    • NCCR demonstrator in the HIF couryard: Construction will probably start in April 2026.
    • Schenck Service & upgrade
      Machines will be maintained and upgraded in February – June 2026.
    • Welding-shop in HIF B floor
      Henry set up a welding toolshop in HIF B-floor in collaboration with the D-BAUG toolshop (ongoing).

    IBK REF Information – January 7th 2026

    Welcome to 2026 in Bauhalle – we wish you worldbreaking scientific experimenting and healthy, motivated next 12 months.

    See current projects here: REF Projects

    QTR 1/2026

    QTR 2/2026

    Welcome Henry – our new Bauhallenteam member

    Henry started as follower of Tomi. Please meet him in or around Bauhalle.
    He brings expert competences in welding and will for sure improve our experimenting quality in future.
    Have a good start in Bauhalle, Henry.

    Project proposal – DEADLINE

    Deadline for new student projects in springsemester 26 is Friday 16th of January 26.
    Use the following link for applying: ProjectProposal

    Revision and upgrade Schenck

    Both Schenck machine will be services end of February (16 – 29. February) and can not be used in this time.

    Bauhalle – New Responsibility list

    Please find the renewed list of responsibilities on site of the project management and Bauhallenteam in the list above.

    Also find it in our sharepoint site: https://ethz.sharepoint.com/sites/PRO-BAUG-00003828

    HPQ – construction site

    More information: HPQ construction


    Introduction courses

    the introduction courses for the coming semester will be published in the next REF-news (February).
    Planned dates will be in the first two weeks of the semester (starting February 16th).
    Please contact Bauhallenteam if you want to be on the waiting list.

    Verdeckten Gefahren auf der Spur – “On the trail of hidden dangers”

    For 2026/2027, the annual theme of Occupational Safety Switzerland is: „On the trail of hidden dangers.“
    https://www.arbeitssicherheitschweiz.ch/de/branchenloesung/jahresthema
    See also the following link from ETH:
    https://ethz.ch/staffnet/en/service/safety-security-health-environment/risk-assessment-and-action-planning.html

    • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
      We are waiting for an evaluation report for possible new locations.
    • 15MN machine (Taras)
      Specification document is in preparation by Bauhallenteam.
    • NCCR demonstrator in the HIF couryard: Construction will probably start in April 2026.
    • Schenck Service & upgrade
      Machines will be maintained and upgraded in February, March 2026.
    • Fork Lift 5t / 2.5t
      Based on the „experimental research @ D-BAUG“ decision which is still discussed in Strategiekommission

    IBK REF Information – December 3rd 2025

    See current projects here: REF Projects

    QTR 4/2025

    QTR 1/2026

    Project proposal – DEADLINE

    Deadline for new student projects in springsemester 26 is Friday 16th of January 26.
    Use the following link for applying: ProjectProposal

    Bauhalle drinking water

    The water supply in Bauhalle and the IBK labs is “modernized” and there is drinking water quality in all taps.

    Bauhalle on ETH landing page
    experimenting is always popular:

    https://ethz.ch/de/news-und-veranstaltungen/eth-news/news/2025/12/was-brandschutz-spezialistinnen-im-eth-master-lernen.html

    Cleaning week

    This years cleaning week will be expanded from 8th till 19th of December.
    Persons conserned will be contacted soon by Bauhalle.
    As always we want to make sure that “Chli stinke muess es” is not true in Bauhalle;)

    HPQ – construction site

    More information: HPQ construction


    Introduction courses

    there is a short term introduction this coming Friday 5th at 9am in Bauhalle.
    Please contact Bauhallenteam if you want to join.

    Safety checklists

    use the help of the SUFA checklists if you are working on the risk assessment of your project.

    • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
      We are waiting for an evaluation report for possible new locations.
    • 15MN machine (Taras)
      Specification document is in preparation by Bauhallenteam.
    • NCCR demonstrator in the HIF couryard: Construction will probably start in April 2026.
    • Schenck Service & upgrade
      Machines will be maintained and upgraded in February, March 2026.
    • Fork Lift 5t / 2.5t
      Based on the „experimental research @ D-BAUG“ decision which is still discussed in Strategiekommission