Monthly Archives: January 2022

IBK REF Information – January 5th 2022

Bauhallenteam wishes healthy and happy working days in 2022.

Situation strong floors

QTR 1/2022

QTR 2/2022

Information

Coronavirus emergency mode

Experimental research is possible following the ETH master plan:
https://ethz.ch/services/en/news-and-events/coronavirus.html
All personal tasks in Bauhalle and IBK labs MUST BE scheduled by Friday of the privious week in the available Bauhallen outlook calendar!
HIF building is only accessable with your batge.

Project registration
Deadline for proposing experimental projects for spring semester 2022 is 7th of January 2022 – hurry.
Fall semester projects must be applied till 1st of July 2022.

HIF (+) restoration

HIF+ Information Site

Area 3.1 of the HIF refurbishment is already closed. Till May 2022 experiments are limited to the old strong floor and LUSET. Therefor early proposal of all projects is required.

Problems with the heating system seem to be solved.
Pay attention to the construction site influences:

  • Noise (Health, Concentration, detection of experimental events..)
  • Vibration (measurement accuracy, Stability)
  • Dust (measurement accuracy, Health, equipment functionality)
  • Climate (can get cold in Bauhalle, <14°C)

BauhallenTEAM(+)

Bauhallenteam is searching for team support. Please forward the advertisment if you know motivated and knowledged persons:
https://jobs.ethz.ch/job/view/JOPG_ethz_VQwYFjvjo7GtEvhaNo

Procurement

  • ASSEMBLY: Hexapod (Chatzi), Installation continues in January 2022
  • FIRE Simulator (Frangi) , delivery May/June 2022
  • Vibrophore (Taras)
  • 15MN machine (Taras)
  • Replacement of Walter&Bai testing machine (financial participation of IfB still open!)