Monthly Archives: June 2022

IBK REF Information – June 1st 2022

New & Running Projects
See current projects here:
REF Projects

Situation strong floors

QTR 2/2022

QTR 3/2022

Information

Schedule all tasks in Bauhalle by Friday of the privious week in the available Bauhallen outlook calendar!

Order and cleanliness

It is a great concern of Bauhallenteam to have a tidy laboratory to do cutting edge science. We therefore rely on the support of all of you to:
– have a orderly project area
– return tools and material if no longer used to it’s proper storage location
– contact Bauhallenteams for other “order and clenliness” questions
PLEASE help us to be proud of Bauhalle – especially yet while HIF is under construction.

HIF (+) restoration

HIF+ Information Site

Phase 3.2 will start in August 2022 , exact dates for Phase 3.3 are not communicated yet.
Bauhallenteam will be occupied with moving tasks for cleaning area 3.2.
MAKE SURE that no material is left in area 3.2 which must be accessed till end of the year!

Replacement for Walter & Bai material testing machine

SEP documents are in preparation in collaboration with IfB. Since the last submission date (1st of May) could not be reached, the request will be treated in September. The goal is the delivery of the new machine with the opening of the renovated lab.

Procurement

  • Hexapod (Chatzi) – delivered, final location unclear
  • FIRE Simulator (Frangi) , delivery Sepbember 2022
  • Vibrophore (Taras)
  • 15MN machine (Taras)
  • Replacement of Walter&Bai testing machine