IBK REF Information – August 7th 2019

New ProjectsNew & Running Projects
See current projects here:
REF Projects

Situation strong floors

Quartal 3/2019

Quartal 4/2019

Information

Bauhallenteam
From August 23rd till end of October the Bauhallenteam will again be decimated cause of holpitalization. Especially toolshop tasks have to be scheduled in advance.

HIF (+) restoration
Excavation work will begin in August which will be the same time where the old gate (see image above “Quartal 4/2019”) will be closed.
More information here:
https://www.ethz.ch/de/campus/entwickeln/bauprojekte/hif-projekt.html

Concrete grinding machine
The grinding machine in room HIF B61 has another defect. Together with IfB the procurement of a new machine is in process. Until then the tasks must be supported by the Bauhallenteam.

Semester Projects
We kindly ask for the proposal of all upcoming experimental projects of the next semester.
Please use Sharepoint to do so.

Könn modular furnace
The control of the furnace extension is still not working properly. Könn is working on a solution which should be available till October.

Fire tests @ EMPA
From mid of July 2019 the fire test facility at EMPA is no longer available. IBK was allowed to secure useful material which is yet stored in room HEZ D27.

Procurement

  • Hexapod (Chatzi)
  • Small fire furnace (Frangi)
  • Test facilities (Taras)
  • New concrete grinding machine (IBK, IfB)