IBK REF Information – December 3rd 2025

See current projects here: REF Projects

QTR 4/2025

QTR 1/2026

Project proposal – DEADLINE

Deadline for new student projects in springsemester 26 is Friday 16th of January 26.
Use the following link for applying: ProjectProposal

Bauhalle drinking water

The water supply in Bauhalle and the IBK labs is “modernized” and there is drinking water quality in all taps.

Bauhalle on ETH landing page
experimenting is always popular:

https://ethz.ch/de/news-und-veranstaltungen/eth-news/news/2025/12/was-brandschutz-spezialistinnen-im-eth-master-lernen.html

Cleaning week

This years cleaning week will be expanded from 8th till 19th of December.
Persons conserned will be contacted soon by Bauhalle.
As always we want to make sure that “Chli stinke muess es” is not true in Bauhalle;)

HPQ – construction site

More information: HPQ construction


Introduction courses

there is a short term introduction this coming Friday 5th at 9am in Bauhalle.
Please contact Bauhallenteam if you want to join.

Safety checklists

use the help of the SUFA checklists if you are working on the risk assessment of your project.

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    We are waiting for an evaluation report for possible new locations.
  • 15MN machine (Taras)
    Specification document is in preparation by Bauhallenteam.
  • NCCR demonstrator in the HIF couryard: Construction will probably start in April 2026.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded in February, March 2026.
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is still discussed in Strategiekommission

IBK REF Information – November 5th 2025

See current projects here: REF Projects

QTR 4/2025

QTR 1/2026

REF project process

In the last time many project managers did not follow the project process for experimental research.
Please start with proposing your projects here and organize a kickoff-meeting in a next step.

More information in paragraph 8.

Water in Bauhalle !! Pay attention

Pay attention that in all sinks in REF laboratories there is no drinking water.
Use the kitchen sinks to get drinking water.
The waterline will be renewed and we will inform if you can drink all sink water again.

HPQ – construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).


Hazard identification

Project management does also include responsibility for a safe experiment. Here are possible hazards which must be thought of before anybody starts testing:
https://www.ekas.admin.ch/en/occupational-health-and-safety/information-for-employers/hazard-identification
You can use our risk assessment sheet to evaluate your project hazards:
IBK_RiskA-Matrix_suva_TOOL_v01.xlsx

Learn from collegues

The first aid RapLab way:

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    We are waiting for an evaluation report for possible new locations.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
    Specification document is in preparation by Bauhallenteam.
  • NCCR demonstrator in the HIF couryard: Construction will probably started in April 2026.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded in the first half of 2026.
  • Lecture earthquake table (Chatzi, Stojadinovic) – will be delivered in December 2025
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is still discussed in Strategiekommission

IBK REF Information – October 1st 2025

See current projects here: REF Projects

QTR 4/2025

QTR 1/2026

Bauhallenteam – staff

The successor for Tomi Jaggi was chosen and will start in January 2026. From mid of October Bauhallenteam will therefore be limited in resources.

Water in Bauhalle !! Pay attention

Pay attention that in all sinks in REF laboratories there is no drinking water.
Use the kitchen sinks to get drinking water.

HPQ – construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).

REF contributors

Bauhallenteam will support the following non IBK groups in experimental research:
– Group de Wolf
– Group Boltshauser
– Group Dillenburger (in discussion, Kaufmann)
Projects of these groups do not require a supporting IBK professor, since they give a contribution to the experimental budget of IBK.


Safety e-learning module

We highly recommend to take the following e-learning module:

https://ethz.ch/staffnet/en/news-and-events/internal-news/archive/2025/06/safety-and-security-at-eth-zurich-new-e-learning-module.html

First aid team

The First Aid Team at ETH Zurich does its part to ensure that members of and guests at ETH Zurich are taken care of as quickly as possible in the event of illness or injury and can be referred to the right care facilities. If you are interested you can also join the team.

Take a look at the handout training: https://ethz.ch/content.download.course?id=140078&name=2022_EHT_Handout_First_aid_at__ETH_EN.pdf&mime=application/pdf

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    Setup locations in Bauhalle will be evaluated for a second time. Possibilities are in the nothern part and on the old strongfloor.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
    Specification document is in preparation by Bauhallenteam. A rough quote for a 10MN machine was received.
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded (Taras)
  • Lecture earthquake table (Chatzi, Stojadinovic)
    Our existing Quanser shaketable will be replyced by a Linmot system:
    https://shop.linmot.com/D/linearmodule-&-f%c3%bchrungen/linearmodule-em01-fm01/linearmodule-fm01-48/module-fm01-48x360f-hp-c/fm01-48-660_200_1cf48x360f-hp-be02-md01-c.htm
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission, all fork lifts shoud be available in a D-BAUG inventory pool.

IBK REF Information – September 3rd 2025

Leave a reply

See current projects here: REF Projects

QTR 3/2025

QTR 3/2025

Project proposal

Please make sure that all experimental projects are registered – that helps Bauhallenteam in scheduling your support.

1) Propose Project on Sharepoint site
2) Make sure that all experimental working persons in the project participated in the “introduction to experimental research @ IBK” course.
3) Organize a Kickoff-meeting

More information here: REF Projects.

HPQ – construction site

More information: HPQ construction
Project is running in time, influences mainly cause effort in future projects at IBK (new machines..).

HIL – living lab project

We want to make you pay attention to the living lab project:
https://ethz.ch/en/campus/development/construction-projects/hil-project.html
Especially because we already experienced the renovation woks in HIF beside running our experimental research. As an institute and department we should learn about our experience.


introduction to experimental research @ IBK” course

The new introduction dates for the coming semester are open for registration – please share:
https://doodle.com/sign-up-sheet/participate/dcd5c871-24f3-433d-8017-aabb88616625/select
For preparation we strongly propose to take the following course:
https://ethz.ch/content/dam/ethz/special-interest/chab/se-management-dam/Hauptseite/EN/Handbuch.pdf

Equipment Inspection

Pay attention to check the green label for all electric devices before you use it (in laboratories).
Equipment Inspection is mandatory at ETH and you can contact Bauhallenteam for support. Also Martin Huber manages test equipment fo the safety check at D-BAUG which can be used by trained persons.

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    Setup locations in Bauhalle will be evaluated for a second time. Possibilities are in the nothern part and on the old strongfloor.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
    Specification document is in preparation by Bauhallenteam.
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded (Taras)
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission, all fork lifts shoud be available in a D-BAUG inventory pool.

IBK REF Information – August 6th 2025

See current projects here: REF Projects

QTR 3/2025

QTR 4/2025

HPQ – construction site

More information: HPQ construction
There are minor impacts with deliveries at the HIF courtyard.

Project proposal

Please make sure that all experimental projects are registered – that helps Bauhallenteam in scheduling your support. DEADLINE for student projects in the coming semester is August 29th.
Experiments at IBK follow a project process. To start a project here are the first steps:

1) Propose Project on Sharepoint site
2) Make sure that all experimental working persons in the project participated in the “introduction to experimental research @ IBK” course.
3) Organize a Kickoff-meeting

More information here: REF Projects.

Bauhallenteam – staff

Tomi will retire by end of the year. This is why we will search a successor soon. The position will be advertised on the ETH platform.

Working hours in IBK laboratories

Always follow the rules of Bauhalle. Very often, people work outside the working hours without permission – please get used to the rules.
https://ethz.sharepoint.com/sites/PRO-BAUG-00003828/SitePages/RULES-in-Bauhalle.aspx

SAFETY ideals – CERN
Read about the safety regulations at CERN.
https://hse.cern/content/safety-regulations-sr
Since orderliness is always a safety issue the following documents also describe topics where we need your help in having a safe experimental environment:

The new introduction dates for the coming semester are open for registration – please share:
https://doodle.com/sign-up-sheet/participate/dcd5c871-24f3-433d-8017-aabb88616625/select
For preparation we strongly propose to take the following course:
https://ethz.ch/content/dam/ethz/special-interest/chab/se-management-dam/Hauptseite/EN/Handbuch.pdf

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    Setup locations in Bauhalle will be evaluated (nothern part with tuned damping system / old strong floor)
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
    Specification document is in preparation by Bauhallenteam.
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission, all fork lifts shoud be available in a D-BAUG inventory pool. After the decision was made, new procurements will be discussed.

IBK REF Information – July 2nd 2025

See current projects here: REF Projects

QTR 3/2025

QTR 4/2025

HPQ – construction site

More information: HPQ constructio
Vibration specifications for the HPQ building ensure, that there are many restrictions to other groups on Hönggerberg. In IBK the Hexapod of Eleni can not be placed in Bauhalle.
Also D-PHYS wants to limit dynamic forces in laboratories.

Summer = vacation time

When planning experiments, please pay attention to the summer vacation of Bauhallenteam.
See Outlook or Calendar in HIF D80.3.

Working hours in IBK laboratories

Always follow the rules of Bauhalle. Very often, people work outside the working hours without permission – please get used to the rules.
https://ethz.sharepoint.com/sites/PRO-BAUG-00003828/SitePages/RULES-in-Bauhalle.aspx

SAFETY @ ETH – new course

We strongly propose to take the following course as soon as possible if you work in the experimental area of IBK.

https://ethz.ch/content/dam/ethz/special-interest/chab/se-management-dam/Hauptseite/EN/Handbuch.pdf

Probably the course will be mandatory for starting the Introduction to experimental research course.

introduction to experimental research @ IBK” course

The new introduction dates for the coming semester are open for registration – please share:
https://doodle.com/sign-up-sheet/participate/dcd5c871-24f3-433d-8017-aabb88616625/select

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building). Report of measurement campaign shows, that the Hexapod can not be located in HIF.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • Schenck Service & upgrade
    Machines will be maintained and upgraded
  • Fork Lift 5t / 2.5t
    Based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission, all fork lifts shoud be available in a D-BAUG inventory pool. After the decision was made, new procurements will be discussed.

IBK REF Information – May 7th 2025

See current projects here: REF Projects

QTR 2/2025

QTR 3/2025

4.4MN Teststand

The 4.4MN teststand on the new strongfloor is getting an update.
Group Frangi is using it for compression tests on timber columns and improves the setup to also make it future proof.

HPQ – construction site

HPQ construction works are in time. Excavation works are almost finished.
More information: HPQ constructio

Collaboration IBK, IBI, Boltshauser

IBK will collaborate with IBI (mainly group de Wolf) and group Boltshauser (ARCH). This includes the support in experiments in Bauhalle.

SAFETY @ ETH – CHAB

If you want to update your safety knowledge theres a lot of information on 132 pages of the CHAB safety manual.

https://ethz.ch/content/dam/ethz/special-interest/chab/se-management-dam/Hauptseite/EN/Handbuch.pdf

introduction to experimental research @ IBK” course

There is a mid semester cours at Friday 9th of May at 9am. Contact Bauhallenteam if you want to attend.

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    New measurement campaign will be started in April 2025. An expertise will be worked out by Ziegler Consultants.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • 5MN loadcells – 3x 6axis loadcells will be procured by the chairs of Stojadinovic and Vassiliou
  • Schenck Service & upgrade
    the Schenck machines should have a service and there is a defect on the large machines column sealing. A quotation is available (about CHF 140k, including new electronics).
  • Fork Lift 5t
    IBK owns the Linde 5t forklift, which is about 25 years old. Quotations are in house for a replacement. The purchase decision should be made based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission.

IBK REF Information – March 5th 2025

Running Projects

See current projects here: REF Projects

QTR 1/2025

QTR 2/2025

Project process

Experiments at IBK follow a project process. To start a project here are the first steps:
1) Propose Project on Sharepoint site
2) Make sure that all experimental working persons in the project participated in the “introduction to experimental research @ IBK” course.
3) Organize a Kickoff-meeting

More information here: REF Projects

HPQ – construction site

HPQ construction works are in time. Excavation works are almost finished.
More information: HPQ constructio

Collaboration IBK, IBI

IBK will collaborate with IBI (mainly group de Wolf). This includes the support in experiments in the IBK experimental area.

SAFETY worlwide

It’s not only us being picky about safety:
“If much of behaviour follows rules, then safety rules are merely that sub-set that improves or achieves safety.”



  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
    New measurement campaign will be started in April 2025. An expertise will be worked out by Ziegler Consultants.
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
  • NCCR demonstrator was approved by Schulleitung. It wil be a rooftop of about 13x6m inside the courtyard of HIF. IBK will use it for outside tasks and storage.
  • 5MN loadcells – 3x 6axis loadcells will be procured by the chairs of Stojadinovic and Vassiliou
  • Schenck Service & upgrade
    the Schenck machines should have a service and there is a defect on the large machines column sealing. A quotation is available (about CHF 140k, including new electronics).
  • Fork Lift 5t
    IBK owns the Linde 5t forklift, which is about 25 years old. Quotations are in house for a replacement. The purchase decision should be made based on the “experimental research @ D-BAUG” decision which is discussed in Zukunftskommission.

IBK REF Information – February 13th 2025

See current projects here: REF Projects

QTR 1/2025

QTR 2/2025

Project proposal

Please make sure that all experimental projects are registered – that helps Bauhallenteam in scheduling your support.
Propose all projects here: REF Projects

HPQ – construction site

HPQ construction works do influence the nothern part of HIF.
More information: HPQ construction, https://youtu.be/6zkJrHMbGCI
Some more media inforamtion: https://hoengger.ch/in-der-grube-auf-dem-hoenggerberg/

Temporary space for chair Boltshauser

Group Boltshauser will use the following area till May 2025 for experiments and construction purpouses.

Collaboration IBK, IBI

Discussions are in progress with IBI to have a collaboration in using technicians in Bauhalle.

Upgrade Bauhallen IT – Win11

Together with Roberto we are updating all Computers in Bauhalle to Windows 11. That causes to replace hardware which is no longer compatible to the new OS.
Please contact Bauhallenteam in case of problems.

Introduction courses

new introduction courses
introduction to experimental research @IBK course or the
– crane introduction
(will be announced according to needs)
Make sure that all experimental working persons need to have the introduction!

SAFETY worlwide

It’s not only us beeng picky about safety – here are the University of Idaho rules:
https://www.uidaho.edu/dfa/division-operations/ehs/tips/basic-safety-rules

  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
  • outdoor cleaning area beside gate 27 (for casting tasks, sedimentation tank) –New GMIS proposal will be placed with location behind Bauhalle – perhaps combined with a demonstrator building of NCCR
  • 5MN loadcells – 3x 6axis loadcells will be procured by the chairs of Stojadinovic and Vassiliou

IBK REF Information – January 9th 2025

Bauhallenteam wishes a healthy, happy and experimental new year to all of you – looking forward to “destroy” for research findings in your projects.

See current projects here: REF Projects

QTR 1/2025

QTR 2/2025

Periodic Equipment Inspection
the experimental part of IBK did the Periodic Equipment Inspection (GeP) | ETH Zurich in November 2024.
Please contact Bauhallenteam if you find an orange or red sticker on a device you want to use!

Project proposal – DEADLINE
17th of January 25 is set for new projects in the upcoming semester.
Propose all projects here: REF Projects

HPQ – construction site
HPQ construction works do influence the nothern part of HIF.
More information: HPQ construction, https://youtu.be/6zkJrHMbGCI

HPQ – construction site
HPQ construction w

Introduction courses

new introduction courses
introduction to experimental research @IBK course or the
– crane introduction
(will be announced according to needs)
Make sure that all experimental working persons need to have the introduction!

SUVA news

The Construction Work Ordinance (Article 23) stipulates fall protection measures from a height of 2 m.
https://www.prona.ch/nouveaute-reglementaire-a-partir-du-01-01-2025-coffrage-de-dalle-mesures-de-protection-contre-les-chutes-des-2m-de-hauteur/

  • New DAQ devices (HBK QuantumX) were delivered
  • Hexapod (Chatzi): Construction project waiting for confirmation from D-PHYS (HPQ building).
  • Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
  • 15MN machine (Taras)
  • outdoor cleaning area beside gate 27 (for casting tasks, sedimentation tank) –New GMIS proposal will be placed with location behind Bauhalle – perhaps combined with a demonstrator building of NCCR