Running Projects
See current projects here: REF Projects
QTR 2/2024

QTR 3/2024

expRES@IBK – process
Use the following link for applying a project: ProjectProposal
Deadline is 1st July 2024 to apply for experimental student projects for the autumn semester.
HPQ – construction site
HPQ construction works do influence the nothern part of HIF.
More information: HPQ construction
HIF refurbishment
There will be a feedback document of the HIF refurbishment to Schulleitung which is in preparation of the Nutzerausschuss.
thefts in Bauhalle
After thefts had stolen computer equipment in Bauhalle the following
measures will be implemented:
- area HIF 104 can only be accessed with ETH badge
- the spiral staircase on the southern side of Bauhalle will be completly seperated from Bauhalle (no access possible)
- C34/36 a manual lock was installed to the gates – please lock gates after leaving
Valuable equipment should be stored in C34/C36!
Walter&Bai testing machine
The new W&B testing machine (5MN, 300kN) machine is delivered. Handover is planned in KW24.
New Equipment
- HBK data acquisition devices (HBM QuantumX)
- Hexapod (Chatzi): Construction project for foundation of Hexapod in nothern part of Bauhalle.
- Vibrophore (Taras) – location in Bauhalle guaranteed inside IfU area
- 15MN machine (Taras)
- outdoor cleaning area beside gate 27 (for casting tasks, sedimentation tank) – GMIS proposal entered – DECLINED (location was wrong – Portfolio should give new location)
New GMIS proposal will be placed with location behind Bauhalle - HEZ – tent for preparation of specimen