New & Running Projects
See current projects here:
REF Projects
Situation strong floors
QTR 2/2022

QTR 3/2022

Information
Schedule all tasks in Bauhalle by Friday of the privious week in the available Bauhallen outlook calendar!
HIF (+) restoration
Phase 3.2 will start in August 2022 – so area 3.2 can be used for experiments in July.
Exact dates for Phase 3.3 are not communicated yet.
Drilling tasks on the Bauhallen floor will be performed in calendar week 18 and 19. There will be severel interruptions of house technics (water, air pressure, light..) in the next months.
ELU – Experienced Lab Users
Bauhallenteam made the first round of evaluating experimental working persons in Bauhalle. The first three months till end of July 2022 is a test phase. Afterwards all rules in the ELU documentation will be followed.
Procurement
- Hexapod (Chatzi) – delivered, final location unclear
- FIRE Simulator (Frangi) , delivery Sepbember 2022
- Vibrophore (Taras)
- 15MN machine (Taras)
- Replacement of Walter&Bai testing machine
SEP documents entered