New & Running Projects
See current projects here:
REF Projects
Situation strong floors
QTR 2/2022

QTR 3/2022

Information
STILL schedule all personal tasks in Bauhalle and IBK by Friday of the privious week in the available Bauhallen outlook calendar!
HIF (+) restoration
Please find extra information to timeshifts in the construction site calendar here:
https://blogs.ethz.ch/BUAG-IBK-Bauhalle/2022/03/28/ibk-ref-information-extra/
Phase 3.2 will start in July 2022 and end by end of the year. Please inform about requirements for planned projects in that timeframe. Bauhallenteam is planning movements of equipment already.
Dominik Werne is new user representative in Nutzerausschuss. Problems/wishes can be sent to him.
There will be severel interruptions of house technics (water, air pressure, light..) in the next three months.
ELU – Experienced Lab Users
Bauhallenteam made the first round of evaluating experimental working persons in Bauhalle. Information will be send out by email.
Procurement
- Hexapod (Chatzi) – delivered, final location unclear
- FIRE Simulator (Frangi) , delivery June 2022
- Vibrophore (Taras)
- 15MN machine (Taras)
- Replacement of Walter&Bai testing machine
SEP documents are in preparation