New & Running Projects
See current projects here:
REF Projects
Situation strong floors
QTR 1/2022

QTR 2/2022

Information
Coronavirus emergency mode
Experimental research is possible following the ETH master plan:
https://ethz.ch/services/en/news-and-events/coronavirus.html
All personal tasks in Bauhalle and IBK labs MUST BE scheduled by Friday of the privious week in the available Bauhallen outlook calendar!
HIF (+) restoration
Area 3.1 of the HIF refurbishment is already closed. Till May 2022 experiments are limited to the old strong floor and LUSET. Therefor early proposal of all projects is required.
In area 3.2 multiple machines/equipment must be protected while the area gets refurbished. Therefore specifications tasks are planned.
Introduction to experimental research @ IBK and crane introduction
Please use the following links to rigister for
– the mandatory introduction to experimental research (English)
https://doodle.com/meeting/participate/id/9avj37na
– the crane introduction
https://doodle.com/meeting/participate/id/7e5WDKqb
BauhallenTEAM(+)
Bauhallenteam is searching for team support.
Interviews are in progress and we expect to have an additional teammember in June/July.
Procurement
- Hexapod (Chatzi)
There is an issue with the planned final location of the system and the new PHYS building HPQ. It is not clear yet if the system can be positioned in Bauhalle. - FIRE Simulator (Frangi) , delivery June 2022
- Vibrophore (Taras)
- 15MN machine (Taras)
- Replacement of Walter&Bai testing machine