11 student projects were proposed till the deadline of 1st July 2021 for the autumn semester.
Situation strong floors
QTR 3/2021

QTR 4/2021

Information
Safety Introduction
all persons working in labs of IBK have to attend the safety introduction course. Please inform concerning persons.
Coronavirus emergency mode
Experimental research is possible following the ETH master plan:
https://ethz.ch/services/en/news-and-events/coronavirus.html
All personal tasks in Bauhalle and IBK labs MUST BE scheduled by Friday of the privious week in the available Bauhallen outlook calendar!
Unplanned tasks will not be supported.
HIF (+) restoration
There will still be construction works around bauhalle which can influence experiments:
- Noise (Health, Concentration, detection of experimental events..)
- Vibration (measurement accuracy, Stability)
- Dust (measurement accuracy, Health, equipment functionality)
In the last weeks there were a lot of interrupts on air pressure system / cooling system.
We will contact the Nutzerausschuss to find a solution for a better communication.
Planning of Phase 3 (Bauhalle) of the refurbishment is still to start in Nov. 2021 with the nothern part of Bauhalle. Since there are delays in Phase 2 – sidelabs of IBK labs are 8 months behind – updates in the schedule are expected till mid of September.
Procurement
- Hexapod (Chatzi), decision made – MTS, will be delivered in Sept/Oct 2021
Release with conditions was granted by Schulleitung for 2021. - Small fire furnace (Frangi) , decision made – E-TERM
Project is granted by Schulleitung. - 1D laser scanner vibrometer (Chatzi)
- Vibrophore (Taras)
- 15MN machine (Taras) (first priority)