New Projects

Running Projects
See running projects here:
REF Projects
See Bauhalle in 3D
https://ibk-baug.sp.ethz.ch/wiki/lab/Pages/Bauhalle-StreetView.aspx
Situation strong floors
Quartal 2/2019

Quartal 3/2019

Information
Bauhallenteam
In Autumn Semester 2019 the Bauhallenteam will again be decimated cause of holpitalization. This must be consideres in project planning.
Prof. Vassilious group will be supported in experiments from now on. This means that in the future there will be less resources for the other groups.
New space
IBK has got access to a storage room in HEZ building. This will be used by the group of Prof. Frangi.
HIF (+) restoration
Groundbreaking is fixed to 8th of July. This will also influence projects in Bauhalle since the event must not be disturbed between 15h00 and 18h00.
Also July must be conisdered for cleaning of the couryard.
Könn modular furnace
The extension of the modular Könn furnace is still not initially tested. There are some open tasks on Könn side, which should be solved till end of July 2019.
WIKI Platform
We want to motivate all IBK members to actively use the WIKI platform:
https://ibk-baug.sp.ethz.ch/wiki/SitePages/Home.aspx
Procurement
- Hexapod (Chatzi)
- Small fire furnace (Frangi)
- Test facilities (Taras)
- New concrete grinding machine (IBK, IfB)